Indians' Football kickoffs the home opener tonight at 7pm!
about 8 years ago, Joe Murphy
Grandparents' Day is today at Chilhowee School! We hope to see all of our elementary students' grandparents today from 1:30pm to 3:00pm!
about 8 years ago, Joe Murphy
The Tax Rate hearing is Wednesday night at 7:00 pm in Room 101 of the school. The public hearing is to discuss the proposed tax rate of the district. The regular meeting will follow the hearing.
about 8 years ago, Chilhowee R-IV Schools
The Regular Board of Education Meeting is tonight Wednesday 15th @ 7:00 pm in Room 101. Items on the Agenda: old business building update, new business setting tax rate, set tuition rate, approve annual secretary of board report, assign program coordinators, approve local compliance plan, Board Policy Resolution, policy BBFA conflict of interest.
about 8 years ago, Chilhowee R-IV Schools
The new whiteboards and projectors are up in the classrooms.
about 8 years ago, Chilhowee R-IV Schools
New Whiteboard are up!
Please join us for the Chilhowee Back to School Bash from 4:30 to 6:30 on Monday, August 13. There will be a Title I meeting at 6:15pm and an Athletics Informational Meeting for Players, Parents, and Fans starting at 6:30pm.
about 8 years ago, Joe Murphy
Chilhowee Junior High Volleyball Practice will Start on Monday, August 13 from 4:00-5:30.
about 8 years ago, Joe Murphy
Chilhowee cheer begins on Monday, August 13th! Practice will run from 7:00 to 7:45 in the morning. You will receive an August practice schedule and additional information at the first practice. Again, set your alarms, this will be a morning practice starting at 7:00am.
about 8 years ago, Joe Murphy
The doors are up and final coat of paint is being applied. Getting closer to the start of school.
about 8 years ago, Chilhowee R-IV Schools
Elementary doors
Breezeway walls are coming down.
about 8 years ago, Chilhowee R-IV Schools
First wall down!
The offices have traded places. The Principal office and attendance window are now at the entrance.
about 8 years ago, Chilhowee R-IV Schools
Jessie's new office!
Janise's New Office!
pad site is almost level, next step is gravel.
about 8 years ago, Chilhowee R-IV Schools
pad site level
The last tiles are being installed. One step closer to the getting the new rooms.
about 8 years ago, Chilhowee R-IV Schools
Last tiles
wall base is done.
They are filling in the pad site to be ready for the next stages.
about 8 years ago, Chilhowee R-IV Schools
Filling in the excavated area
The pad site is ready to be filled for the new building.
about 8 years ago, Chilhowee R-IV Schools
the pad site is ready to be filled.
The old building basement has been removed.
about 8 years ago, Chilhowee R-IV Schools
old basement walls are gone.
New floors have started
about 8 years ago, Chilhowee R-IV Schools
New hall floor
the old locker room walls are being removed.
about 8 years ago, Chilhowee R-IV Schools
foundation of old building
foundation walls
They found the old building
about 8 years ago, Chilhowee R-IV Schools
walls of the old building
back wall of old building.
Excavation has started on the new addition.
about 8 years ago, Chilhowee R-IV Schools
Excavation starting